● Location: Sichuan, China
● Project capacity: phase Ⅰ 2.47MMSCFD (7×104 Nm3/d), phase Ⅱ 10.6MMSCFD (35×104 Nm3/d)
● Construction period: phase Ⅰ 2014.6~2015.1, phase Ⅱ 2014.7~2016.1
● Main processes: MDEA sweetening, TSA dehydration, SMR liquefaction
● Product temperature: -160℃
● Scope: EPC
● Design flexibility: 50%~110%
● Total power consumption: phase Ⅰ 0.395 kWh/Nm3, phase Ⅱ 0.506 kWh/Nm3
(The feed gas pressure of phase Ⅱ is lower than that of phaseⅠ)